Locks and Dams

Corps Completes 34-Day Closure At Holt Lock And Dam

As it weaves through the wooded hills of Tuscaloosa County, Ala., the Black Warrior River tumbles from an elevation of near 240 feet to below 100 feet in a span of less than 30 miles. In centuries past, that precipitous drop produced rocky, shallow rapids as the river plowed through what is now downtown Tuscaloosa. Today, that drop in elevation is eased by a trio of structures: John Hollis Bankhead Lock and Dam at Black Warrior River Mile 365.5, Holt Lock and Dam at Mile 347 and Oliver Lock and Dam at Mile 337.7.

The U.S. Army Corps of Engineers owns and operates a total of six locks and dams on the Black Warrior-Tombigbee Waterway that all measure 110 feet by 600 feet. Bankhead and Holt offer by far the highest lifts on the system at 68 feet and 64 feet, respectively, with Oliver adding another 28-foot lift.

The Corps team that manages the Black Warrior-Tombigbee Waterway along with lock maintenance contractor R&D Maintenance Services Inc. and Barnhart Crane & Rigging, is wrapping up a major repair project at Holt Lock, which first opened to navigation in 1966.

The primary task during the 34-day closure at Holt, which began July 10, was replacing the lock’s lower miter gate. G&G Steel of Russellville, Ala., fabricated the new gate leafs and transported them to the lock by barge from their facility in Iuka, Miss., via the Tennessee-Tombigbee Waterway, then up the Black Warrior River. The new gate leafs arrived on site ahead of schedule on July 2.

Just as they did two years ago at Selden Lock and Dam farther downriver, the maintenance team at Holt used a gantry crane spanning the lock chamber to lift and lower the old gate leafs onto a deck barge and to install the new leafs.

“It’s a pretty unique way of doing it,” said Danny Hensley, Corps operations project manager for the Black Warrior-Tombigbee and Alabama River waterways. “Other Corps of Engineers districts don’t use a gantry to remove and set gate leafs, but it works well for us.”

The sprawling Barnhart gantry crane used in the operation was made up of two 150-foot-long, 8-foot-tall girders spanning the lock chamber. Each weighed 230,000 pounds. Atop the girders was a hoist with a lifting capacity of 500 tons.

Removing the old gate leafs and setting the new leafs in the gate recesses on temporary stands was a methodical process that spanned four days.

“It takes approximately 3-1/2 to 4 hours to move the hoist from one side of the lock chamber to the other,” said Brooks Ferguson, project manager with R&D Maintenance, which oversees lock and dam maintenance and recreation facility maintenance for the Corps on the waterway. “We took one gate leaf down then stood up the new gate. We made a lift a day.”

The first new leaf was set on a brand-new nickel pintle ball July 30, with the other leaf set August 1.

“Most people don’t realize nickel is a valuable metal used in alloys to make things other than nickels,” Hensley joked.

Ferguson said the new leafs each weigh about 375 tons—35 tons more than the old leafs. The new leafs each feature three positive and three negative “gate diagonals,” which are adjustable, angled tension rods. G&G pre-stressed the gate in its fabrication facility, and the Corps team had the ability to adjust the diagonals after the gates were set using hydraulic jacks. The redesign of the gate diagonals was a lesson learned from Selden in 2016, Hensley said.

“At Selden, we opened three days late,” Hensley said. “Those three days are attributed to having to stress the gates with heat and turnbuckles. We realized that was an area we needed to save time in.”

Hensley said pre-stressing the gates at the fabrication shop with the hydraulic jacks worked so well that no additional adjustments were required at the lock.

The new gate leafs also feature low-voltage anodes for reducing corrosion and synthetic timbers, among other modernizations.  At the top connection of the new leafs, the Corps also repaired the mule head anchors, which is where the leaf ties into the chamber lock wall.

“Over the years, they’d line-bored those several times,” said Anthony Perkins, navigation manager for the waterway. “The hole was originally 6 inches, now it’s almost 7. We’re having to come back with a special radial welding machine to weld those up, then line bore them back to the original size.”

Other Work

And while the new lower miter gate was the most pressing task at Holt, the team was busy elsewhere at the lock throughout the month-long closure.

The Corps replaced much of the hydraulic piping located in galleries at the lock, which is critical to operating the valves that flood the chamber. Those pipes were heavily corroded from decades of use in a damp environment. The new carbon steel piping features a ceramic coating to fight corrosion.

“The rust incorporates into the ceramic coating,” Hensley said. “The new coating is supposed to be something that can handle the damp conditions.”

In all, about 1,200 feet of piping was replaced at Holt.

“That’s almost a quarter mile of pipe,” said Wynne Fuller, operations division chief for the Mobile Engineer District.While the upper reach of the waterway was closed, the Corps also replaced 200 feet of piping at Bankhead Lock, Hensley said. West Alabama Mechanical Inc. of Moundville, Ala., was the subcontractor in charge of replacing the pipe.

Crews were also busy making repairs to the smaller upper miter gate at Holt Lock during the closure.

As part of the contract to fabricate the new miter gate, G&G is also building new valves for Holt Lock. Hensley said those will be delivered in 2019.

“These valves have been problematic over the years with vibrating issues, and have required many repairs,” he said. “We’ve had more trouble with valves here than at any other lock. They’ve been redesigned, rebuilt, and they’ll be put in one at a time without having to close the lock to traffic.”

Dewatered Chamber

One surprising sight at the bottom of the dewatered lock chamber: bedrock.

“They left this rock instead of taking it out and pouring concrete,” Hensley said. “They just left it, and it forms the floor of the chamber. I guess it saved on concrete and rock removal. They wouldn’t do that now, but we haven’t had any issues with it. They just left the natural rock and poured around it.”

Besides the usual tools, tires and rims, walnuts, bolts and driftwood found on the floor of the dewatered chamber, maintenance crews and visitors also spotted an occasional hunk of coal among the debris. That’s no surprise, since coal is such a vital cargo on the Black Warrior River, with several large coal mines on the upper reaches of the waterway.

“Our biggest commodity is coal,” lock supervisor Ashley Ward said.

The vast majority of tonnage passing through Holt Lock is metallurgical coal bound for export from the Port of Mobile.

And now with the new miter gate at Holt, the entire Black Warrior-Tombigbee Waterway is up-to-date on lock maintenance and in good working order. That reliability throughout the system is a great driver of commerce, said Larry Merrihew, president of the Warrior-Tombigbee Waterway Association.

“Because we have such an efficient river system, thanks to what the Corps is doing to keep these locks running, we’re seeing more and more economic development opportunities,” Merrihew said.

Slideshow from Holt Lock dewatering (all photos by Frank McCormack):

Holt Lock 034 Holt Lock 002 Holt Lock 013 Holt Lock 030 Holt Lock 041 Holt Lock 036 Holt Lock 025 Holt Lock 010
<
>