Repairs at Wilson Lock and Dam are expected to be complete and the chamber reopened on July 8. While work is still ongoing, several key tasks have been completed, allowing… Read More
Locks and Dams
Better guidance on when the main chamber of Wilson Lock will return to service should be available in the first week to 10 days of June, according to the Nashville… Read More
The Corps of Engineers released its Fiscal Year 2025 Work Plan May 15, with funds allocated for Chickamauga, Montgomery and T.J. O’Brien Locks. The Bayou Sorrel Study also received funding. Read More
Crews are more than two months into the projected three-month repair of upstream miter gates in the main chamber at New Cumberland Locks and Dam, Ohio River Mile 54.3. The… Read More
The opening of the main navigational lock chamber at Wilson Locks and Dam has been delayed by approximately three weeks, until early July instead of June 14. The Nashville Engineer… Read More
Construction of a new, 600- by 110-foot lock at Chickamauga Lock and Dam on the Tennessee River has reached two major milestones, with crews beginning to erect the new lock’s… Read More
More than six months after the closure of Wilson Lock’s main chamber, ports, shippers, fleeting services, linehaul operations and other river-related businesses say it is costing them. In some cases,… Read More
The St. Louis Engineer District announced April 15 that the main, 1,200-foot lock chamber at Melvin Price Lock and Dam (Lock and Dam 26) has reopened. The project required a… Read More
The Corps of Engineers reopened the navigational lock at Lockport Lock and Dam on the Illinois River April 4 after crews discovered damage to the lock’s lower miter gates during… Read More
The American Society of Civil Engineers (ASCE) released its latest Infrastructure Report Card on March 25. While ports overall earned a B, dams and levees got only a D-plus, and… Read More